BBWF: Combined Effects Assessment Meeting

There was a meeting in the Innerwick Village Hall on Monday, to discuss the Addendum to the Environmental Impact Assessment Report submitted by Berwick Bank Wind Farm (BBWF) to the Council Planning department. There is a note of the meeting as well as Dom’s marked up copy of the Annotated Addendum produced by BBWF.

A particular point to note is that as suggested by Gary Donlin of BBWF, we applied for a two week extension to the deadline for submission of Representations on this Addendum to the EIAR. The deadline has therefore been extended to October 2nd 2023.

Notes from Community meeting with Berwick Bank Wind Farm Ltd (BBWF)


11th September 2023
Innerwick Village Hall
Attendees from BBWF:
Gary Donlin
James Wheater
Keira Jamieson

East Lothian Winds of Change (ELWOC):
Dom Moynihan (Chair)
Lesley Gordon-Smith
Hazel
Tracy Dart
Kevan Jamieson
Maria Isotalo
Ian Dart

Councillors:
Lyn Jardine (East Lothian: Dunbar & East Linton)

  • 30 people in attendance.
  • Brief discussion on the bullet point summary of Dom’s comments on the Addendum to the Environmental Impact Assessment Report (EIAR).
  • A copy of the Addendum to the EIAR including Dom’s marked up comments will be made available on the ELCC website.
  • BBWF described two meetings that have taken place between ‘the Other Developers’ planning to construct electrical infrastructure in East Lammermuir Community. Gary commented that detailed Construction Traffic Management Plans until Tier 1 Contractors are appointed, which has not yet happened. Tier 1 Contractors are what used to be referred to as ‘Main Contractors’ and may also be referred to as ‘Principal Contractors’ in the context of Health & Safety legislation.
  • Gary did commit to including representatives from the Community in these meetings, particularly in relation to Construction Traffic.
  • Developers are apparently working on a Joint Charter to which they will all sign up. This Charter will commit Developers to adherence to principles yet to be defined. This Charter will also include details as to how these Charter Principles & Commitments will be enforced, following a question in relation to such enforcement from Lyn Jardine.
  • Gary also reported that there is agreement in principle for Developers to fund an independent ‘Monitoring & Coordinating officer.’ This person will act as a bridge between Developers & the Community.
  • BBWF, following a question from Lesley, committed not to use Thornton Bridge for any form of Construction traffic.
  • Kevan enquired as to the part played (or not) by East Lothian Council in selecting the site for the BBWF substation. Gary promised to check & revert back to Kevan.
  • Noise: Hazel questioned the anticipated noise output from the substation once in operational mode. After a lengthy discussion regarding background noise levels, maximum noise levels and perceived noise level. BBWF offered to send a Noise Consultant to talk to the residents of Crowhill, given the latter’s location as closest to the proposed BBWF substation.
  • Gary stated that whilst final design optioneering had not been concluded, the current chosen electrical design indicated that an HV DC converter station would not be required and that the electricity would come ashore as AC. This was widely welcomed by the attendees in the Hall.
  • The point was made to Gary that given Crowhill’s close proximity to the planned BBWF substation, a concerted effort and closer consultation with the Crowhill residents was merited. This was accepted by Gary.

East Lothian Infrastructure – Traffic Management Meeting

Wind Turbine Blades

Meeting @ Innerwick Village Hall

Thursday 27th July @ 6.30pm

This is a meeting about TRAFFIC:

A working group meeting to pull together all our thoughts and ideas on what we need to communicate to the various infrastructure project developers on how they work/behave on our roads whilst ‘visiting’ our area.

It is documented that there will be a significant increase in traffic on our roads, both main trunk and narrow country lanes. The developers acknowledge the impact from HGV’s, noise and dust will be severe.

All welcome for this initial meeting before we make a smaller working group.

Please come along and give us your ideas!

We would appreciate an idea of those intending to attend so please email if you plan to attend: email East Lothian Winds of Change

Contact Details:

Contact us for more information and to be added to the distribution list for news updates.

email East Lothian Winds of Change

facebook https://www.facebook.com

EAST LOTHIAN INFRASTRUCTURE PROJECTS

off shore wind farm

The next 10 years will see an unprecedented number of critical National Energy Infrastructure projects constructed in East Lothian, both on and offshore.

Plans are already under way for the Berwick Bank Wind Farm, Branxton Battery Energy Storage, North Belton Battery Energy Storage, Crystal Rig IV onshore Windfarm, Crystal Rig solar farm, Newlands Hill Wind Energy Hub (Windfarm), Capping off and restoration of Oxwellmains Landfill and the Eastern Link project, as well as the decommissioning of Torness Power Station.

Each of the projects is expected to bring hundreds of workers to the area, but concerns have been expressed about where they will stay, additional traffic on the road and ensuring that the area reaps the benefits.

Innerwick and its surrounding villages and hamlets are on the frontline, being on the main route taken by the cables and construction traffic. Stenton and Spott are impacted to a lesser extent by the development at North Belton. Stenton will be affected by views of the Newlands Hill turbines on the skyline to the south and possibly by construction traffic, the routes are not yet known.

Berwick Bank Wind Farm, which has already secured a grid connection at Branxton, near Torness, will be created 40 kilometres off the county coast and feature more than 200 turbines, the largest windfarm in Europe and possibly the world.

Braxton and Belton Battery Storage facilities are to help match energy demand at peaks with the wind generation available by storing energy at peak generation and releasing it at peak demand.

Fred Olsen Renewables will be adding a further 11 turbines and a Solar Farm at their Crystal Rig site up in the Lammermuir hills

The Eastern Link project involves more than £1.5 billion of underwater cabling linking Thorntonloch Beach, near the East Lothian town, to County Durham. This will form part of the backbone of the UK’s energy supply.

Finally, Torness Power Station is expected to stop generating power in March 2028. De-fuelling and decommissioning is expected to last for around 20 years

Boundaries of the main projects – darker shades show overlapping areas
Berwick Bank onshore Planning Boundary

Berwick Bank Onshore application for Planning Permission in Principle (PPP) submitted April 2023, deadline for Representations closed May 23. No date for anticipated Determination Date advertised by ELC.

Onshore PPP granted by ELC May 2023. more …

Branxton Energy Bank Planning Boundary

Branxton Energy Bank: The 4 month consultation period for ELC to submit comments to ECU ends 6th August 2023. No advertised date for ECU determination but expected to be 2024. Grid connection is late 2027 so Construction, ECU Consent depending, could start early 2027 but not likely to be before this due to fixed grid connection date. more …

Crystal Rig Phase IV and Solar

Crystal Rig Phase IV:
11 turbines up to 200m, 42MW
Construction commences Q3 2023
Route to site will be A1 to Innerwick Junction then south to site entrance
Crystal Rig Solar:
30MW solar array
Public consultation ongoing. more …

Dunbar Battery Energy Storage System at North Belton

Dunbar Battery Energy Storage: FRV TH Powertek are building a 49.9MW Battery Energy Storage System (BESS) is proposed, 850m north of Pitcox and 3km south west of Dunbar.
Underground cable to the point of connection (substation immediately south of the site). more …

Eastern Link Planning Boundary

Eastern Link: Braxton Substation: Planning Permission in Principle (PPP) application submitted to ELC in June 2023. Application not yet validated by ELC

Converter Station at Oxwell Mains Landfill: Planning Permission in Principle (PPP) granted by ELC in May 2023. Marine licence also granted by Scot Gov for marine cables. more …

Neart na Gaoithe (NnG) offshore wind farm

The Neart na Gaoithe (NnG) offshore wind farm will be located 15.5 km off the Fife coast and covers an area of approximately 105 km2. EDF Renewables UK acquired the project in May 2018 as part of a competitive bidding process. Completing is expected Q1 2024. more …

Newlands Hill Wind Energy Hub

Newlands Hill Wind Energy Hub: The proposal is for 17 turbines with tip heights ranging from 180m to 200m. Located approximately 6km SE of Gifford and 9km South of Stenton, with a capacity up to 112MW.    Construction traffic and grid connection routes have not been provided yet.  Planning application 2023, with target completion 2027. more…

Torness is due to end generation in March 2028.

Torness Defueling begins when a station stops generating in 2028. EDF will remove all spent fuel from the site using the same methods used during generation. Defueling is expected to last for approximately four years, followed by a further 12 years decommissioning. The site will be cleared sometime after 2044. more …

Project Plan Tracker
Project Timeline
Compulsory Purchase Order Plots for Berwick Bank Wind Farms

Contact Details:

Contact us for more information and to be added to the distribution list for news updates.

email East Lothian Winds of Change

facebook https://www.facebook.com

Developer Contacts:

DevelopmentCompanyContact details
Eastern Link / Oxwellmains Converter station / Branxton sub-stationSPENeasternlink@spenergynetworks.co.uk
Berwick Bank Landfall / Skateraw Converter StationSSEGary Donlin gary.donlin@sse.com
Neart na Gaoithe windfarmNnGinfo@nngoffshorewind.com  
Crystal Rig IV & Solar FarmFred Olsen RenewablesKirsty Leiper kirsty.leiper@fredolsen.com www.crystalrigwindfarm.co.uk
Branxton Energy  Storage FacilityEast Coast Grid Services Ltd.  Steve Ruggi
steve.ruggi@gridcodepower.com   http://branxtonenergystorage.com/
Dunbar Battery Energy Storage SystemSirius Planning representing FRV PowertekDan Elvin dan.elvin@thesiriusgroup.com
Decommissioning of TornessEDFAshleigh.dickson@edf-energy.com
Newlands Hill Wind Energy HubBelltown PowerMatt Olley matt.olley@belltownpower.com Sam McMillan sam.mcmillan@mcmillan.scot https://www.newlandshillwindenergyhub.com/
Oxwellmains LandfillValenciabe confirmed
Table of Developer Contact Details

Regulatory & Government Contacts:

Energy Consents Unit (ECU)
Econsents_Admin@gov.scotThis is the division of Scottish Government that deal with developments covered by the Electricity Act 1989. Applications under Section 36 of this Act go directly to ECU & are determined by the ECU, albeit via consultation with the relevant local authority. 
jayne.anderson@gov.scotCase Officer for DPEA.
Appointed Reporter is Paul Cackette.
East Lothian Council (ELC)
dproudfoot@eastlothian.gov.ukDouglas Proudfoot, ELC Executive Director of Place (aka head of planning).
kdingwall@eastlothian.gov.uk Keith Dingwall, ELC Planning Service Manager. 
Elected Representatives –
MPs & MSPs
kenny.macaskill.mp@parliament.ukKenny Macaskill, MP for East Lothian, Alba Party
paul.mclennan.msp@parliament.scotPaul MacLennan, MSP East Lothian & SNP Housing Minister.
Martin.Whitfield.msp@parliament.scotMartin Whitfield List MSP for South Scotland.
Local Councillors:
ljardine1@eastlothian.gov.ukLyn Jardine, Dunbar & East Linton Ward SNP.