Torness Underground Cable Replacement Works to Commence January 11th 2016

SP Energy NetworksSP Energy Networks (SPEN) is shortly due to commence the replacement of a section of ageing underground cable which runs from Torness Power Station to Branxton Substation.

Preparatory work and mobilisation will commence 11 January 2016 with the programme of works scheduled to run through to completion in November 2016, barring any unforeseen developments. To progress the project as quickly as possible and reduce the term of impact on the community, they plan to work on a seven day basis.